16Hydrometers Operation and Maintenance Manual
Operational Testing
INSTALLATION
Before the hydrometer is placed into service, you should perform the following tests to verify that
it is operating properly:
A. To test water ow and manual operation:
Set 3-Way Selector to the “Open position”.
Turn on the water ow to the hydrometer.
Visually verify that water is owing downstream from the hydrometer in appropriate
quantities.
Verify that the leak detector, pointers and the totalizer are functioning properly.
Check all hoses, connections, pilot valves, etc. for leakage and repair as necessary.
Set 3-Way Selector to the “Close position”.
Verify that the water ow downstream has stopped.
B. To test automatic and remote operation:
Set 3-Way Selector to the “Auto” position.
Turn on the water ow to hydrometer.
Verify that the hydrometer output is correctly received by the controller or control center.
Use the controller or control center to close the hydrometer. Verify that the water ow
downstream has stopped.
Use the controller software to test operation of the hydrometer under various applications
and conditions such as pressure reducing, pressure sustaining and ow regulation.
Your hydrometer is now ready for routine use.